Do you need a permit to pour a driveway, patio, or slab in Humble, TX?
Yes, and plans with it. Humble is an incorporated city with its own Building & Inspection Department, and the city’s building page lists concrete among the projects that need a plan submission. If your address is inside Humble’s city limits, Houston’s rules and the county’s aren’t the ones that matter for the slab itself. Humble’s are.
The desk is at City Hall, 114 W. Higgins Street, and the number is 281-446-6228. Everything below comes from the city’s building page and its Residential Plan Packet as posted in September 2026. The packet is a 2020 document with a fee schedule updated in October 2024, so check anything that matters with the desk.
What the packet asks for on flatwork
The concrete line in the packet is short and specific. For pads, driveways, and slabs, it asks for:
From the packet, for flatwork
- Two sets of plans that show the rebar size and spacing
- #4 rebar at 12 inches center to center through the first 10 feet of the driveway approach, the stretch that meets the street
- Silt fencing on the job
Then there’s the inspection list. Under residential building, it names “Slab/Rebar” and “Driveway/Rebar,” which means the steel gets looked at while it’s still visible. Plan for that stop between setting the steel and ordering the truck.

A slab for a shop or garage asks for more
A slab that will carry a building, like a detached garage or a shop, falls under the packet’s checklist for new buildings, shops, garages, and additions. That list adds:
- A plot plan with setback lines: 25 feet in front, 10 feet in back, and 7½ feet on the sides
- The floodway location marked on the site plan
- A survey of the property
- A soil report, with the holes and piers calculated and stamped by an engineer
Height matters too. Outside the floodplain, the packet says a concrete slab floor has to sit at least 12 inches above the top of the nearest sanitary sewer manhole or the crown of the nearest street, whichever is higher. Inside the floodplain, new residential structures go two feet or more above what the packet calls the 500-year flood level.
Check the floodplain first
The city’s building page is blunt about this one. Research the 100-year and 500-year floodplain before any activity, and that includes fill in any amount, grading, and storage. It also warns that a floodplain development permit is often required even when a construction permit may not be. On a patio that raises the grade, that’s the question to answer first.
Fees, and what skipping the permit costs
The fee schedule in the packet took effect October 1, 2024. A few lines matter for concrete work:
- Plan review runs half the permit cost.
- Re-inspections cost $50 the first time, $75 the second, and $100 after that.
- Work started before the required permits are issued is charged double the permit fees, on top of any citation from code enforcement.
Who can pull it
This is where the packet leaves real gaps, so here’s what it says and what it doesn’t.
It includes a contractor registration page. Contractors register with the City of Humble using a registration form, a driver’s license, and a certificate of insurance for at least $250,000 that names the city as certificate holder. A general contractor can send a representative; state license holders have to show up in person. The technical code page lists building work under the 2018 International Building and Residential Codes as “No License Required,” so this is a city registration, not a state license.
The fee schedule also lists a $50 Home Owner Exemption Permit that requires proof of a homestead exemption. The packet doesn’t say what that permit covers. If you’re thinking of pulling it yourself, ask the desk what it allows before you plan around it.
Before you hire anyone in Humble
Ask who is pulling the permit, and whether they’re registered with the city.
Our part on a Humble job
We aren’t registered with the City of Humble, so we don’t pull permits there ourselves. We check what your address needs and draw the two plan sets the packet asks for, approach steel included. Then we coordinate with whoever pulls the permit so the rebar inspection lands before the truck does.
For a garage or shop pad, our slab page covers the spec. For the local picture, see our Humble page.
Permit rules change, and the City of Humble has the final word for your address. We last checked the city’s building page and Residential Plan Packet in September 2026. This is general information, not legal advice.
Sources
- City of Humble: Contractor Registration application (2021) (cityofhumbletx.gov)
- City of Humble: Building & Inspection Department (cityofhumbletx.gov)